Retainage
Retainage is a portion of each progress payment, often around 5 to 10 percent, that a client withholds until a project is complete or accepted.
The contractor has earned that money but cannot collect it yet. It belongs on the books as retainage receivable, separate from ordinary accounts receivable.
Example
On a $100,000 contract with 10 percent retainage, each $20,000 progress bill pays out $18,000 and holds back $2,000. After five bills, $10,000 is earned but still held.
Common mistake
Leaving retainage inside regular AR. It makes the aging report look worse than reality and hides cash that will not arrive until closeout.
How to use it
Track retainage per job, note the release conditions in the contract, and bill for release as soon as they are met.
Why clients hold retainage
Retainage gives the owner some protection that the work will be finished and corrected before the last payment goes out. The amount and the release terms are set in the contract, and rules about retainage can differ by state and by type of project, so read your contract and ask your attorney about local rules. For the contractor, the practical effect is the same: you have earned the money but you cannot spend it yet.
How to record it
Bill the full progress amount, then show the held portion as retainage receivable. The customer pays the net amount, and the retainage balance stays open on that job until it is released. If you owe retainage to your own subcontractors, record that separately as retainage payable. Keeping both sides visible lets you see how much cash is tied up on each job and when it is expected to come back.
Retainage and your own cash flow
Retainage can add up quickly on a business with several jobs open at once. Ten percent held on each of five projects is a meaningful amount of money you cannot use for payroll, materials or taxes. When you plan cash, count retainage as money that arrives at job closeout, not on the billing date. If you carry retainage on subcontractors you pay, hold it consistently and release it under the same conditions you agreed to, so the paperwork matches what you pay. Reviewing retainage by job each month also shows which projects are tying up the most cash.
Getting retainage released
Retainage is often forgotten at the end of a job. Note the release conditions at the start, such as final inspection, punch list completion or lien waivers. When the conditions are met, send the release invoice promptly and follow up like any other receivable. Review open retainage monthly alongside your aging report, so money held on finished jobs does not sit for months without anyone asking for it.